summaryrefslogtreecommitdiff
path: root/Master/texmf-dist/tex/latex/heria/hi-workplan.tex
diff options
context:
space:
mode:
Diffstat (limited to 'Master/texmf-dist/tex/latex/heria/hi-workplan.tex')
-rw-r--r--Master/texmf-dist/tex/latex/heria/hi-workplan.tex21
1 files changed, 21 insertions, 0 deletions
diff --git a/Master/texmf-dist/tex/latex/heria/hi-workplan.tex b/Master/texmf-dist/tex/latex/heria/hi-workplan.tex
index 20070b17c37..db64e7da4eb 100644
--- a/Master/texmf-dist/tex/latex/heria/hi-workplan.tex
+++ b/Master/texmf-dist/tex/latex/heria/hi-workplan.tex
@@ -40,12 +40,33 @@ Please provide the following:
\item
\emph{Give full details. Base your account on the logical structure of
the project and the stages in which it is to be carried out.}
+\makeatletter
+\ifdim\@templateversion pt<3.4pt
\emph{The number of work packages should be proportionate to the scale
and complexity of the project.}
\item
\emph{You should give enough detail in each work package to justify
the proposed resources to be allocated and also quantified information
so that progress can be monitored, including by the Commission}
+\else
+ \emph{Each work package should be a substantial part of the work
+ plan, and the number of work packages should be proportionate to
+ the scale and complexity of the project.}
+\item \emph{Structure each work package by breaking it down into
+ tasks. If tasks are not appropriate, work packages can be
+ organised according to other criteria (e.g., according to the type
+ of work or thematically). For each task or element of the work
+ package, describe all activities to be carried out and quantify
+ them (e.g., number of protocols, tests, measurements,
+ combinations, study subjects, conferences, publications,
+ etc.). Provide enough detail to clarify who will do this work and
+ why it is needed for the project, (e.g., the level of
+ qualification and number of person-months for personnel, as well
+ as the requested equipment, consumables, meetings, etc.), to
+ justify the proposed resources and so that progress can be
+ monitored, including by the Commission.}
+\fi
+\makeatother
\item
\emph{Resources assigned to work packages should be in line with their
objectives and deliverables. You are advised to include a distinct